HSR Campus Planning Information

Current Status of Overall Development at the High-Speed Rail Campus (Former Xingzhong Branch)

2011.09.26 Approval of the establishment plan announced by the Executive Yuan
2012.03.15 The Executive Yuan notified the Ministry of Education to change the property to non-public use according to Article 33 of the National Property Act, and to allocate it for use according to Article 38 of the same law
2012.04.23 Completed free allocation of the Huwei Air Force Base from the Ministry of National Defense
2012.05.02 Completed land management registration
2012.07.24 Entrusted the Construction and Planning Agency, Ministry of the Interior, to handle the “Xingzhong Branch Land Development Planning and Permit Amendment Project”
2014.03.11 The Central Regional Water Resources Bureau, Ministry of Economic Affairs, gave principle approval for the water usage plan
2015.11.13 Entrusted the Central Regional Engineering Office, Ministry of the Interior, to professionally handle “Xingzhong Branch Land Grading, Drainage, and Other Public Facility Projects”
2015.11.25 The Environmental Impact Assessment Review Committee held its 291st meeting and recommended approval of the environmental impact assessment
2016.04.28 The Ministry of the Interior’s Regional Planning Committee held its 374th meeting and approved the project
2017.03.02 The Ministry of Education approved the finalized conceptual plan for land grading, drainage, and public facilities construction
2017.07.27 Groundbreaking ceremony for land grading, drainage, and public facilities construction
2018.03.15 The Ministry of Education approved the “Phase 1 Building Construction Concept Plan of Xingzhong Branch” (NT$480 million version)
2018.08.21 The Ministry of the Interior replied to Yunlin County Government agreeing to reduce development impact fees to 50% of the required amount
2018.11 Completed land grading, drainage, and public facility works
2018.11.19 Yunlin County Government approved the land use change for the campus
2019.04.06 Completed inspection of land grading, drainage, and public facilities; handover ceremony held on April 25
2019.06.28 The Ministry of Education approved the revised “Phase 1 Building Construction Concept Plan of Xingzhong Branch” (NT$560 million version) in principle
2019.07.30 Huwei Land Office completed land subdivision work
2019.08.21 Huwei Land Office approved the land use change
2019.09.05 Yunlin County Government issued completion certificate for land grading and drainage
2021.04.15 Groundbreaking ceremony for Phase 1, Section 1
2021.06.23 The Ministry of Education approved the revised “Phase 1 New Building Construction Plan” second amendment (NT$820 million version) in principle
2022.03.14 Beam-raising ceremony for Phase 1, Section 1 – Practice Workshop
2022.10.04 Renamed as “High-Speed Rail Campus” (approved by Administrative Meeting)
2022.10.07 Construction of Phase 1, Section 2 commenced
2023.09.25 Phase 1, Section 1 construction completed (usage permit obtained)
Estimated by end of 2025 Phase 1, Section 2 construction completion

 

Current Status of Phase 1 New Construction by Section

Section 1

Construction started on April 26, 2021, and obtained the usage permit on September 25, 2023.

Section 2

Construction started on October 7, 2022, and is expected to be completed by October 7, 2025.
As of September 14, 2025, planned progress was 85.01%, actual progress 86.07%. Current construction status of each building is as follows:
 (1) International Industry-Academia Cooperation Building: interior decoration, MEP works, and outdoor landscaping in progress.
 (2) Practice Workshop: roof, interior decoration, MEP works, and outdoor landscaping in progress.
 (3) Campus Gate Guardhouse: interior decoration, MEP works, and outdoor landscaping in progress.

Data last updated: 2025.09.24