HSR Campus Planning Information
Current Status of Overall Development at the High-Speed Rail Campus (Former Xingzhong Branch)
| 2011.09.26 | Approval of the establishment plan announced by the Executive Yuan |
| 2012.03.15 | The Executive Yuan notified the Ministry of Education to change the property to non-public use according to Article 33 of the National Property Act, and to allocate it for use according to Article 38 of the same law |
| 2012.04.23 | Completed free allocation of the Huwei Air Force Base from the Ministry of National Defense |
| 2012.05.02 | Completed land management registration |
| 2012.07.24 | Entrusted the Construction and Planning Agency, Ministry of the Interior, to handle the “Xingzhong Branch Land Development Planning and Permit Amendment Project” |
| 2014.03.11 | The Central Regional Water Resources Bureau, Ministry of Economic Affairs, gave principle approval for the water usage plan |
| 2015.11.13 | Entrusted the Central Regional Engineering Office, Ministry of the Interior, to professionally handle “Xingzhong Branch Land Grading, Drainage, and Other Public Facility Projects” |
| 2015.11.25 | The Environmental Impact Assessment Review Committee held its 291st meeting and recommended approval of the environmental impact assessment |
| 2016.04.28 | The Ministry of the Interior’s Regional Planning Committee held its 374th meeting and approved the project |
| 2017.03.02 | The Ministry of Education approved the finalized conceptual plan for land grading, drainage, and public facilities construction |
| 2017.07.27 | Groundbreaking ceremony for land grading, drainage, and public facilities construction |
| 2018.03.15 | The Ministry of Education approved the “Phase 1 Building Construction Concept Plan of Xingzhong Branch” (NT$480 million version) |
| 2018.08.21 | The Ministry of the Interior replied to Yunlin County Government agreeing to reduce development impact fees to 50% of the required amount |
| 2018.11 | Completed land grading, drainage, and public facility works |
| 2018.11.19 | Yunlin County Government approved the land use change for the campus |
| 2019.04.06 | Completed inspection of land grading, drainage, and public facilities; handover ceremony held on April 25 |
| 2019.06.28 | The Ministry of Education approved the revised “Phase 1 Building Construction Concept Plan of Xingzhong Branch” (NT$560 million version) in principle |
| 2019.07.30 | Huwei Land Office completed land subdivision work |
| 2019.08.21 | Huwei Land Office approved the land use change |
| 2019.09.05 | Yunlin County Government issued completion certificate for land grading and drainage |
| 2021.04.15 | Groundbreaking ceremony for Phase 1, Section 1 |
| 2021.06.23 | The Ministry of Education approved the revised “Phase 1 New Building Construction Plan” second amendment (NT$820 million version) in principle |
| 2022.03.14 | Beam-raising ceremony for Phase 1, Section 1 – Practice Workshop |
| 2022.10.04 | Renamed as “High-Speed Rail Campus” (approved by Administrative Meeting) |
| 2022.10.07 | Construction of Phase 1, Section 2 commenced |
| 2023.09.25 | Phase 1, Section 1 construction completed (usage permit obtained) |
| Estimated by end of 2025 | Phase 1, Section 2 construction completion |
Current Status of Phase 1 New Construction by Section
| Section 1 |
Construction started on April 26, 2021, and obtained the usage permit on September 25, 2023. |
| Section 2 |
Construction started on October 7, 2022, and is expected to be completed by October 7, 2025. |
Data last updated: 2025.09.24